Today, we plan to pour a couple of the sidewalk crosswalks between Spring and Ann. We will also be backfilling the green areas between those streets. We hope to pour flowable fill concrete in the [...]
Today we hope to finish the underground work on the South side between Catherine and Spring. We will still have to cross main to the Island for the new Fire Hydrant. Thank you for bearing with us [...]
Today we will continue the new water service work on the South Side between Catherine and Spring. Electrical work is continuing in the same area. We will be pouring concrete in the driveways [...]
Today we will be backfilling the electrical conduit excavation between Catherine and Spring on the South. We will also be installing the new water services to the buildings in the same area. On [...]
Today we will be continuing the concrete driveway pouring on the North Side of Main. We will also be continuing the installation of the wiring underground on the North Side. We hope to start the [...]
Yesterday we attempted to progress. We were able to do some demolition between Catherine and Spring on the South Side of Main. We also invested some time and money into cutting out the wet areas [...]
We would like to think that today we could continue the curb and gutter work on the North side of Main. Wet subgrade conditions may stop that. The new waterline installed between Catherine and [...]
If the weather allows, we will be trying to continue with the progress of the sidewalk and curb and gutter construction on the North Side of Main. On the South Side we will be trying to install a [...]