Streetscape – September 3, 2015

Today we will be pouring island curb at the intersection of Tugaloo and Main on the North Side. We will continue forming for curb at College and Main. We are still waiting on Duke Power to change [...]

0

Streetscape – September 2, 2015

For those who are paying attention to the streets, you noticed the middle of the road changing. The traffic devices are in the shape of the future islands. We started demolition today and will [...]

0

Streetscape – September 1, 2015

Today you will notice that we will be placing traffic barrels in the middle of the road. This is for us to survey and position the future islands. Then we will be taking out the asphalt in the [...]

0

Streetscape – August 31, 2015

Today we are going to clean up from our Concrete pours at the intersection of College and Main and Catherine and Main. We will be installing the Handicap Domes in the Crosswalk areas. On the [...]

0

Streetscape – August 28, 2015

Electrical conduit work continuing at intersection of North College and Main. We hope to cross North College today. On the South side we will be pouring sidewalk and flume at Catherine and Main [...]

0

Streetscape August 27, 2015

As you can see, the excavation between College and Tugaloo on the North side of Main is massive. We are installing the conduit and pull boxes to move the overhead power to underground for the [...]

0

Streetscape – August 26, 2015

The North side of Main seems to be going faster than the South side did because of the fact that there is no new waterline to install. The time consuming factor will be the overhead electrical to [...]

0

Streetscape – August 25, 2015

Continuing Electrical Conduit on the North side of Main. Should move to the block from College to Tugaloo today. Tip island curb and sidewalk work on the South side of Main. We will need to close [...]

0

Streetscape – August 24, 2015

Electrical Conduit work today on the North Side of Main. Concrete work will include forming for the H/C Crosswalks on the South Side of Main. The volume of rain will delay starts until we can [...]

0

Streetscape – August 21, 2015

Demolition is complete between Catherine and Tugaloo. Some dress-up and cleanup will occur today. Electrical conduit will start Monday. We will be trying to return some parking on the North Side [...]