Today we will continue with the sidewalk pouring on the North side of Main. Fort Hill will finish the gas line work in front of Arby’s. Striping will start between Tugaloo and Catherine.

Please pay attention to both entrances to the 4 block construction area. They will change in striping to create a turning lane to the left and right and one center lane to go thru town. These will be at the intersection of Ann and Main on the East Side and also at the intersection of Tugaloo and Main on the west side.

The striping of the one lane thru town will be done on the first two blocks and completed. The area next to the parking is not a travel lane, it is a back up lane out of the parking areas. You can park and back out of the parking into that lane and then merge into the main travel lane.