We would like to think that today we could continue the curb and gutter work on the North side of Main. Wet subgrade conditions may stop that. The new waterline installed between Catherine and Spring on the South side passed the pressure test today. Bac T samples were taken today and will be taken again tomorrow. After results on Thursday we will start the new water service work on that block
Hutch-N-Son Construction

Recent Posts
Contact Us

Thank you for contacting the City of Walhalla. Someone will respond within 5 business days.

Not readable? Change text. captcha txt

Start typing and press Enter to search