Today we will continue the milling of the asphalt between College and Catherine. We will be researching the sewer elevations on the South Side of Main between Spring and Ann. Electrical wire pulling is continuing and hopefully soon we will have street lights on the South side between Tugaloo and Catherine.

In the next few days the milling of asphalt, cleanup and new asphalt paving will affect the traffic patterns between Tugaloo and Catherine. Please pay attention to the flagmen and machinery for safety.

Hutch-N-Son Construction