Today we will be pouring island curb at the intersection of Tugaloo and Main on the North Side. We will continue forming for curb at College and Main.

We are still waiting on Duke Power to change over the power on the North Side. When they do the poles can be removed and we can start the straight line curb work on the North Side on both blocks. Demolition is complete in the two islands and Electrical conduit work will be started today to get electrical conduits to the islands.