- Stumphouse Mountain Park Fee Station
- Sertoma Concessions & Restrooms
- New Police Department
- Water and Sewer Projects
- Sertoma Bridge
Stumphouse Mountain Park fee station area: This project will allow the city to collect fees from visitors to assist with the upkeep of the park.
90% complete.
All major work complete, finishing electrical work and final paneling.
Expected completion on building -May 1st.
Entry gate installation expected installation late spring.
Sertoma Concessions and Restrooms
70% complete
Interior work is ongoing with electrical work nearly complete.
Plumbing and finish work ongoing.
Expected completion date late spring, depending on contractor availability.
New Police Station
3% complete
Design-Build Project awarded to JM Cope.
The design, planning and permit phase is well underway.
Groundbreaking date to be announced soon.
Expected completion date 2026.
April 2025 Progress Report for the City of Walhalla’s SCIIP A-23-C202
WATER AND SEWER IMPROVEMENTS PROJECT
Div I – Gravity Sewer Rehab
The Division I contractor has completed the cleaning and inspection of the gravity sewers and are mobilizing the Cured In Place Pipe equipment and crews to begin the sewer line rehabilitation process.
Next month the contractor expects to continue installing the cured in place pipe and begin point repairs on the gravity sewer lines.
Div. II – Water System Improvements
The Division II contractor is working through the process of ordering the Rocky Knoll water booster pump station equipment and building. The water booster pump station will take several months for fabrication and delivery. The contractor plans to wait until a firm delivery date of the water booster pump station before installing the new water main along SC 28 Highland Highway.
Div. III – Water System Rehabilitation
The Division III contractor is installing the roadway bores and water main along W. North Broad Street.
Next month the contractor expects to continue installing water mains along and around W. North Broad Street and West Main Street.
Sertoma Bridge Replacement
Several quotes have been received to repair the bridge.
The city is working with FEMA to determine if any funds from Hurricane Helene can assist with repairs.