We will be continuing the asphalt process between Tugaloo and Catherine today. I can’t speak for anyone else, but I think that it is looking good. Hopefully we will be complete after today [...]
As you noticed the asphalt work has started. Please be careful driving as we progress with it. The lane closures and the machinery and manpower will be congested between Tugaloo and Catherine. [...]
We feel that our employees deserve a pat on the back. Even with the rain showers we were able to continue with the sewer between Ann and Spring Streets. Today we will continue that sewer [...]
Thank you for your patience yesterday on the traffic congestion at Ann and Main Street. We were able to make the sewer tie in and get out of the roadway. We got a little late but it was [...]
Yesterday we tried to get something done, even with the drizzle and the wet conditions. We were able to do asphalt patching on North College and in the parking lot behind the Police Station. We [...]
Again, yesterday we were outdone by the weather. We look at it like who’s going to win? The weather or us. We will keep trying until eventually we will win and get to complete something. [...]
As I try and plan today, I hear the raindrops hitting the roof!!! If possible we will try and finish the sewer behind the Police Station. Paving between Tugaloo and Catherine is out of the [...]