Today we will continue pouring sidewalks on the North Side of Main. We will continue prepping for more sidewalks between College and Catherine. Electrical work is continuing. We also may be [...]
We poured the driveway to the gas station at Tugaloo yesterday and it will reopen today. We will be pouring sidewalks on the North side of Main. Electrical work is continuing. We will be prepping [...]
For the people that noticed, there are NEW red fire hydrants in the center islands. Some people question that decision. These fire hydrants are positioned perfectly for the Fire Trucks to access [...]
Today the sidewalk is completely open from Tugaloo to Catherine on the South Side. We will be grading for the sidewalk construction on the North Side of Main. Electrical work is continuing as [...]
We feel that we accomplished a lot yesterday. Today we will be continuing the signal light conduit on the North Side of Main. We will also be prepping for sidewalks. We will be continuing the [...]
Today we plan to continue the curb and gutter work on the North side of Main. We will also be installing the conduit for the Signal work on the North side. We will be pouring concrete for the [...]
God bless you all today on a very sad anniversary of our country. 14 years ago our Country was attacked. Today take a moment to remember all of the suffering and death of our people and troops. [...]
As everybody witnessed the weather did not cooperate with us yesterday. We attempted to continue but were stopped. Today weather permitting, we will be working on the backfill of the center [...]
I think we survived the island curb pouring today. There will be more work in the islands, such as Hydrant installation and backfill. This work will happen after we pour the curb on the North [...]