Today the sidewalk is completely open from Tugaloo to Catherine on the South Side. We will be grading for the sidewalk construction on the North Side of Main. Electrical work […]
We feel that we accomplished a lot yesterday. Today we will be continuing the signal light conduit on the North Side of Main. We will also be prepping for sidewalks. […]
Today we plan to continue the curb and gutter work on the North side of Main. We will also be installing the conduit for the Signal work on the North […]
God bless you all today on a very sad anniversary of our country. 14 years ago our Country was attacked. Today take a moment to remember all of the suffering […]
As everybody witnessed the weather did not cooperate with us yesterday. We attempted to continue but were stopped. Today weather permitting, we will be working on the backfill of the […]
I think we survived the island curb pouring today. There will be more work in the islands, such as Hydrant installation and backfill. This work will happen after we pour […]
Today we will be starting curb work in the islands in the center of the Main. Please be careful we will have concrete trucks, curb machine and a lot of […]
We will be continuing the island curb and gutter today. About 8:30 or when the traffic clears we will be closing Main from College to Tugaloo to remove the two […]
Today we will be pouring island curb at the intersection of Tugaloo and Main on the North Side. We will continue forming for curb at College and Main. We are […]
For those who are paying attention to the streets, you noticed the middle of the road changing. The traffic devices are in the shape of the future islands. We started […]