Finally, new sidewalks and driveways in front of Bantam Chef. Thank you Bantam Chef for your cooperation. Thanks to Martha’s, we were able to run conduit thru the side parking […]
We would like to thank you for your patience during yesterdays road closure. We were able to get 15 Electrical and Phone conduits across Main to the North side of […]
We hope that you noticed a change in the work last week as reconstruction has started. Curb work will continue today on both blocks. Electrical work will continue. If everything […]
Tugaloo to College; As you noticed curb and gutter started yesterday. More today. College to Catherine: Curb work and Electrical work. We have experienced some problems with the grades on […]
Sorry Folks about the other E-Mails. There will not be a closing of the side parking lots at the corner of College and Main Monday and Tuesday. I will not […]
Tugaloo to College: Cleaning up and grading, getting ready for curb and gutter and sidewalks. College to Catherine: Working on electrical Conduit and light pole bases. Hutch-n-Son Construction
Tugaloo to College: Light pole bases are ready to pour. College to Catherine: Excavation partially done for electrical conduits. Hopefully installed today. Electrical work is slower than water [...]
Good Morning from Hutch-n-Son Tugaloo to College: Getting ready for reconstruction this week. New curb and gutter should start Thursday, followed by new sidewalk. College to Catherine: Electrical [...]
Yesterday, we were able to get the electrical conduit across College Street, along with tying in an existing 6″ into the new 8″ water main. We were able to abandon […]
Good Morning Everyone, I realize that everybody is ready for this project to be over. Underground utilities are the major slow-down of this project. A lot of things are underground […]