Finally, new sidewalks and driveways in front of Bantam Chef. Thank you Bantam Chef for your cooperation. Thanks to Martha’s, we were able to run conduit thru the side parking lot for [...]
We would like to thank you for your patience during yesterdays road closure. We were able to get 15 Electrical and Phone conduits across Main to the North side of the street. Concrete sidewalk [...]
We hope that you noticed a change in the work last week as reconstruction has started. Curb work will continue today on both blocks. Electrical work will continue. If everything goes well, we [...]
Tugaloo to College; As you noticed curb and gutter started yesterday. More today. College to Catherine: Curb work and Electrical work. We have experienced some problems with the grades on the [...]
Sorry Folks about the other E-Mails. There will not be a closing of the side parking lots at the corner of College and Main Monday and Tuesday. I will not close them until Main is open and [...]
Tugaloo to College: Cleaning up and grading, getting ready for curb and gutter and sidewalks. College to Catherine: Working on electrical Conduit and light pole bases. Hutch-n-Son Construction
Tugaloo to College: Light pole bases are ready to pour. College to Catherine: Excavation partially done for electrical conduits. Hopefully installed today. Electrical work is slower than water [...]
Good Morning from Hutch-n-Son Tugaloo to College: Getting ready for reconstruction this week. New curb and gutter should start Thursday, followed by new sidewalk. College to Catherine: Electrical [...]
Yesterday, we were able to get the electrical conduit across College Street, along with tying in an existing 6″ into the new 8″ water main. We were able to abandon the old water line [...]
Good Morning Everyone, I realize that everybody is ready for this project to be over. Underground utilities are the major slow-down of this project. A lot of things are underground that we do not [...]