Our job today is to continue what we were doing yesterday. The job is to try and make this years OKtober Fest the best ever for the City of Walhalla, […]
Yesterday, we had good cooperation with Duke Power that allowed a lot of overhead power to be transferred to underground. We were able to remove 5 of the old light […]
Our waterline pressure test pasted yesterday. BACT sample was taken also, with one more sample we will be able to start the changeover the services to the buildings from Catherine […]
Today we will be testing the new waterline installed between Catherine and Ann. We will also be continuing on the electrical work for the change over from overhead to underground […]
Today we will continue the new waterline between Catherine and Spring on the North Side. Electrical conduit is continuing with the wire being pulled. We hope this week get some […]
Today we will continue with the electrical conduit, signal light conduit and waterline installation between Catherine and Ann Streets on the North Side of Main. Duke Power showed up yesterday [...]
Today we will continue the ditch excavation for the electrical conduit, traffic light conduit and new waterline between Catherine and Ann Streets. Electrical wire pulling for the new street [...]
We completed the concrete in the ditch lines yesterday between Tugaloo and Catherine. Thank you for being patient with the traffic movement. Today we will continue electrical conduit between [...]
Yesterday we finished the major demo of the streets from Spring and Ann. We also poured part of the concrete in the road crossings. Today we will finish the concrete […]
As everyone noticed, the weather for the last few days has not been good for the construction business. We will be cleaning up today from the rain. We also hope […]