Yesterday, we were able to get the electrical conduit across College Street, along with tying in an existing 6″ into the new 8″ water main.

We were able to abandon the old water line from Tugaloo to College.

College Street was opened back up last evening.

Tugaloo to College:

More light pole base work.

College to Catherine:

More electrical conduit work and cleanup.

Hutch-n-Son Construction